BrightPath Active Learning The project was a 6-month build. Total Site Development 46,914 Sq Ft, Building 6,589 Sq Ft. We started the ground-up project at the beginning of COVID-19, which created a multitude of issues, first and foremost being the steel building factory shutting down for 2 months. We were able to overcome the pre-fab building factory delays due to COVID by re-working and re-phasing our original project schedule. Project Size:46914Project Duration:6 Months PrevPrev Project View all Projects NextNext Project